Just the bare minimum jobs now until the 2nd coat goes on in about 3 weeks. Here are some progress shots show you the past month.
1. Starting of the Top & Bottom Plates - 8th to 13th Oct.
2. Up goes the window & door frames - 14th & 15th Oct.
3. The straw bale walls going up - 14th to 18th Oct.
4. Roof trusses on - 20th to 24th Oct.
5. Colorbond on - 27th to 30th Oct.
6. 1st Coat of render - 1st to 5th Nov.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEh5bHOZOLSiBLmH7XGKAW_vWYRGddH6rtHOBIxJJWR-2LXI9XJhoZeN_xlNUsRRPPs7cjMBwEFMvy4eR3ELcASXIaMzOF-fJ6bgYd5Q35uvBBEG403QnLMRHImRm7GZSrwSD2XtPdaJwjts/s200/08102010%2528016%2529.jpg)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjwIRBkknIyZj-d2dK7cjhyphenhyphen_OsQs5X1EqDbyiE_PG0Gikr2GsWw2u7dSnu5J0VeGbEDEWrgrns4boX9EX623T1ClwVbn_dVsrsjWJUh1HLbgUnjRxf39NaEazt0Gqu5_xiu-AAAH-Uo9kW5/s200/14102010%2528005%2529.jpg)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhAIIfd6nr4mhclsJVWNdR1NQQXABu8OCsXcbs53Qz2QOKn6-4rFIY993HR8EzctpJzheWeZH7LAsx_BTHMUbSSrkvQLgV6u1INL8rORtnWLANfdIrbWYHtU-Y59DNCvqpkUJexRDBchPoX/s200/07112010.jpg)
Hey thanks man!! you are so good. I think this the perfect work.
ReplyDeleteHouses in Australia