Just the bare minimum jobs now until the 2nd coat goes on in about 3 weeks. Here are some progress shots show you the past month.
1. Starting of the Top & Bottom Plates - 8th to 13th Oct.
2. Up goes the window & door frames - 14th & 15th Oct.
3. The straw bale walls going up - 14th to 18th Oct.
4. Roof trusses on - 20th to 24th Oct.
5. Colorbond on - 27th to 30th Oct.
6. 1st Coat of render - 1st to 5th Nov.