1. Trenches dug for Electrical & Phone Line.
These will be installed next week
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEi39uSM6cYDex3mY2GRwcY1SUoSFCRe5Q6HnXST_Rp86dBI1-AAQMt2LRmEEAk4-hHG6sOVVzMuDXM_FO8dINXFLUG61e8IEENUMX0bYGROBdNJKIhkE4_u6idsHq1YibL-8O7OeM9OESV1/s200/03092010(025).jpg)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEj44KZjYD1ijYKtbVmOwelcXKGIDOER68FUEeQ1mo66APF2GjpyoPj-GryJ0Giry3TNYY-kReZ0xD9INPys4LDYtW5Cxth4yTFrcppd6RHRriHVJ0ZcrC91GGvjnIH9J-g4j1coDOAb6tHD/s200/03092010(010).jpg)
2. Water Supply & Storm Water Line
We ran both water supply lines as well as storm water to the house for two reasons;
1. Water supply, from our tank, during the build.
2. The storm water in the same trench for then the roof goes on we can fill out tank right away. We actually had a tanker deliver about 40,000L as well.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhCsGbkpHB7PuaNx3FbAxtCs-ZAZkChPKLvMjtGOL2Ej7_ia32Dy3p2Gsp90yfyBC0C5PFWV0H_qBPw6JVP4lqjV_y_kWc4uhL0tJEtk90i-Irg0gMV5vW66sL2nZAt2DYiA7knVTK7HZS0/s200/03092010(004).jpg)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjViNVbipNju6P0HKTAxBp9Rr_92F53OcrKmiQOUqhTunlQG1POXJYuPg2vrmM664oLWqsEsVYbr28d4GH4Y6YYutGJJ8pXVfm-jPpEhyphenhyphen-tAXYrciXi6MjlTZojzcniAE9CRLdNfjmvJ9d_/s200/03092010(013).jpg)
Preparing pipes for in the tank & first lot of storm water in
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEj25ST2qov4vgnwyh0sj74Uhk1So4z14t9VuiLFtrm5eZrdyjLXMP_KBz9dGpHes-aR35LAh8Nt7rRazNmAJ_gjuC3GTROsRxsAIG2dQvcLum0nmYM4mG6zd62UWDpJ6TGmBl9gtllwkBur/s200/03092010(016).jpg)
![](http://4.bp.blogspot.com/_tC7BnJq20pc/TIb63iBBgdI/AAAAAAAAASc/mYeQXz_HaPw/s200/03092010(006).jpg)
Storm water pipe in as well as 40,000L
(Doesn't look like much)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhfW5Omg1kSebUSPw0Wkz-zqWWbdXDIrs_g8HYTqCq0EcUeNwpOAZ3SRit2mIfsOI-ZG8iGIlAZqFeFvPMnqzqcIta7v-hRv_Tdrh5mHB-FpQW35HCL5P26-1DUmdKadfTSG9QKb20A5FSk/s200/03092010(021).jpg)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhDXStBTosc0Zp9eNxogV4QbcMsTUkwHUznI0IvgGMvkZxxj6WxHfsENDZTNg9kRqiN0atTqkcoeEzKJ5s54tzVvQhIs9H1W2N7u_Aa5JN8RxIQHS2r6rIiTtXGTbWN0xAPQuTtO3f18P05/s200/03092010(046).jpg)
Covering pipes with river sand and now neatly covered.
3. Cutting of Drive Way & Drainage
The guy from Barkers excavation was great, could not have got a better guy to do the job. I was expecting him to take 2 or 3 days & he did it in 1 and did an exceptional job. Thanks mate.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjYCn0FdkBvRHm6TAq-c2mv1S7suU7lRo-IVcdfX2Qp650GfyY3fsAeo6eM0zbu0gvCsVOiYuTEuYIrlE_t-kyJsoB_sDLYluciSvK9yPN_SmTKcb8JOwTMmJO1wkRlsO6k-X0y1Yr5aSol/s200/03092010(019).jpg)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjsvg6wJUa2ze-qWJpaAgzG346Yu1nF1OSHdKDkeCfEtS1k8OXRoqrcEw-nZC8l9JpCJtKourq70oQwWIdf13Lbx6hyphenhyphenes84f1ffsogQv72A_1Tee9TVv2BBn3MiZrYgz65Rd18nUrhtkHB3/s200/03092010(029).jpg)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEiw5JtIFSLV9SggZw8I1xM5jhj5naYfdNAAA-3qjH1iJ7SnVIHjse0sYzXrOUzeX-YDY6tcsnIv7jDG78reSX7XVgaBTh78Jytx6yDeQYd129aJxpTN52K1sMLSmtEh_0QAFQhw2mGSlX3i/s200/03092010(031).jpg)
![](http://2.bp.blogspot.com/_tC7BnJq20pc/TIb8TL8FPoI/AAAAAAAAATs/-LNO10pqV8c/s200/03092010(036).jpg)
Note: The lower 2 pictures area before & after shot after Greg & I used some of the many rock's we have onsite!